About Us The Survey Insurance Claims Guarantees Finance Contact Us Recent Projects Links
 

Wall Ties

Wall tie corrosion is affecting many properties in the UK, especially in coastal and exposed locations. The mild steel or galvanised wire ties embedded into the mortar eventually start to corrode. In its advanced stages, the corrosion will cause horizontal cracking and eventually loss of stability between the two skins of brickwork.

 

 

 

This photograph is taken using the Allen Inspector Scope attached to a Sony Mavica camera. Ideal for inclusion within Structural Engineers reports.

The design of cavity walls invariably incorporates the use of metal wall ties, and this system has been in use since the beginning of the nineteenth century, to prevent rain penetration and to improve thermal insulation. Cavity Wall-ties are an integral support in walls constructed with a cavity between the inner (load bearing skin of masonry), and the outer (weather shield), skin. The outer skin is normally very thin in relation to its height, and without support, would be subject to damage by extreme weather conditions.


Research by the BRE (Building Research Establishment), has found that wall ties corrode faster within the mortar joints of the external leaf of brickwork, where rust builds up around the ‘fish tail’ ends of the ties. This expansion will cause blistering of the mortar joints (at tie courses) creating consequential structural instability
Over recent years, it has become apparent that a high number of properties, built prior to the early 1980s are suffering from cavity wall tie failure, due to corrosion of the metal. This is principally due to poor quality galvanising standards prior to that time. There is also evidence that many properties have been constructed with a lack of density of the original cavity wall tie system, particularly around reveals. Visual evidence of corrosion can be seen by horizontal cracking to the mortar joints of external wall surfaces, or hairline cracking to external render. If corrosion is severe, or neglected for an extended period, this may lead to bulging of the wall.

 

 

 

Horizontal cracking of the mortar joint


However, it is important to note that a property does not need to be in excess of 100 years old to require remedial wall tie work! Over the past few years, we have experienced the need to install a supplementary wall tie system when insufficient ties have been found in relatively ‘new build’ property, only discovered when changing the window casings!
The location of a property will have a significant bearing on the state of corrosion, and this will inevitably vary around the country. For example, on the south cost of Kent and Sussex, exposed southern facing elevations deteriorate quicker than the remainder of the property, requiring only partial replacement (but to the complete affected elevation). The opposite may be the case in the North West and North East of the country.

 

 

 

A wall tie in the flesh.


Back

WALL TIE REPLACEMENT SPECIFICATION
The following specification is the our specification for full wall tie replacement. Unless stated otherwise in our inspection reports, allowance will have been made in the specification for the following works:

• Erection and dismantling of any ladder access necessary to complete works safely. Any requirement for additional access, such as scaffolding or towers, will be at additional cost.

• Location of the existing cavity wall ties irons using a specialist metal detector.

• Installation of stainless steel wall ties spaced and positioned in accordance with current BRE329/401 recommendations.

• Random ‘pull out’ testing of several new ties using a hydraulic tension tester, in order to ensure that a correct fixing has been achieved, and that the most suitable model of tie is being used.

• Where necessary, the structural isolation of remaining ties over affected areas, in order to ensure no further damage can occur as a result of corrosion. (This method of immobilizing of the original ties is dependent on the condition of any samples which are first removed and inspected).

• Structural isolation of the original wall tie system is not always necessary. Where wire (butterfly) ties have been used, isolation would not normally be required.

• Occasionally full removal of the original system is necessary, particularly where internal cracking has resulted from corrosion. This is rare and will usually be the result of a Structural Engineers recommendation.

• The making good of any brickwork, render or mortar disturbed during the installation process. This does NOT allow for specialist types of render finish, pebbledash or plastic coatings. External redecoration will NOT have been allowed for. We will NOT accept responsibility for disturbing pre existing faulty or blown render.

• Removal of any debris created by the works, leaving the adjacent site or garden in a clean and tidy condition.


IMMOBILISATION (ISOLATION):
Apart from the installation of new stainless steel wall ties, the most important aspect in wall tie replacement is the correct immobilization of the original cavity wall ties.
When cavity wall ties corrode they expand, this expansion causes characteristic horizontal cracking which appears in external walls, at ‘tie courses’. This expansion can eventually lead to serious damage occurring. This may then require extensive rebuilding. In view of this it is essential that the original ties are properly immobilized by structural isolation (see para 5 above).
Wall tie replacement is a structural repair. We employ our own trained installation technicians and do not employ ‘labour only’ contractors to do wall tie work. During the course of repairs the interests of property owners are protected by the maintenance of a £5,000,000 public liability insurance.


GUARANTEE:
We are registered installers and a member of the Wall Tie Installers Federation (WTIF) and are approved to issue WTIF Insured Warranties on completed works. The Warranty is valid for 25 years and is transferable to any new owner of the property. For avoidance of doubt the obligation to indemnify extends to all damages, costs expenses and liabilities arising as a result of any financial loss incurred by our customers pursuant to the wall ties and workmanship failing to perform their intended function.

Some banks and building societies prefer to have this sort of structural repair work supervised and the completed workmanship certified by Consulting Engineers or Chartered Building Surveyors. We can arrange for works to be independently supervised and the completed workmanship certified, however independent supervision does involve additional costs in line with the engineer’s fees.


THE NEW TIES:
We only use Remedial Ties from corrosion resistant ‘18/18’ stainless steel. Our technicians use sensitive hydraulic ‘pull out’ equipment to test every job done, thus ensuring complete quality control. No one make or model of wall tie is right for all buildings. We are not connected or ‘tied’ to any manufacturer of wall ties, and will install the tie most suitable for the property. Random testing is carried out using the Hilti ’Pull Test’ kit to 1.5kn (or to a strength specified by a structural engineer, which would normally be 1.5kn).

Back

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
Head Office DWCUK.COM Ltd, 53 Elm Road, Leigh-on-Sea, Essex SS9 1SP
Company Registration No. 3164016 | VAT No. GB 752 4082 43
Contact Us
© DWCUK.COM Ltd 2008